File #: 20-2132    Version: 1
Type: Consent Staff Report Status: Passed
File created: 11/9/2020 In control: Board of County Commissioners
On agenda: 11/17/2020 Final action:
Title: Approval of Work Order No. MM-1 with Kimley-Horn and Associates, Inc. for Structural Design of the Moorhen Marsh Low Energy Aquatic Plant System Redesign
Indexes: Public Works, Stormwater
Attachments: 1. Staff Report, 2. Work Order No. MM-1, 3. Facility Cast-in-Place Structures -Workplan
Related files: 19-0420, 19-0421, 19-0586, 19-1176, 19-1221, 20-1526, 20-1580, 20-1854, 21-0544, 21-0543, 23-0039, 21-0426, 22-0282

Title

Approval of Work Order No. MM-1 with Kimley-Horn and Associates, Inc. for Structural Design of the Moorhen Marsh Low Energy Aquatic Plant System Redesign

Recommended Action

Staff recommends the Board approve Work Order No. MM-1 in the amount of $46,555, executed by Kimley-Horn and Associates, Inc. and authorize the Chairman to execute it on behalf of the County