Title

Sector 7 Beach and Dune Restoration Project Update

Recommended Action

In accordance with the BCC approval of the BSPAC Amended Option 3 at the May 2, 2023 Commission meeting, and with the 30-day easement extension having lapsed, Staff is now requesting approval from the BCC to cancel the current Sector 7 Beach and Dune Restoration Project and seek reallocation of any funds to other Sectors