File #: 22-0184    Version: 1
Type: Department Staff Report Status: Agenda Ready
File created: 2/25/2022 In control: Public Works
On agenda: 3/8/2022 Final action: 3/8/2022
Title: Sector 7 Beach and Dune Restoration Project Easement Status and Project
Indexes: Coastal Engineering, Public Works
Attachments: 1. Staff Report, 2. Letter from BPSAC in support of Option 2
Related files: 20-1729, 21-0636, 20-1737, 17-1198, 18-1498, 19-0571, 20-1654, 20-1978, 20-1980, 18-1329, 19-0050, 19-0602, 19-0720, 21-0972, 23-0528

Title

Sector 7 Beach and Dune Restoration Project Easement Status and Project

Recommended Action

Staff recommends Option 3 to the Board. The easement issue is at an impasse and while staff continues to reach out to property owners to obtain easements, there is very little chance that the County will obtain enough easements to make the project viable. Additionally, staff has been unable to locate property that could be used for construction access to the Sector 7 beach, thereby substantially increasing the cost for the project even if easements are obtained.