File #: 19-0624    Version: 1
Type: Consent Staff Report Status: Passed
File created: 7/8/2019 In control: Board of County Commissioners
On agenda: 7/16/2019 Final action:
Title: 58th Avenue Resurfacing/Reclamation from 26th Street to 49th Street, Release of Retainage and Change Order No. 1 (IRC-1324, FM No. 434840-1-54-01)
Indexes: Change Order, Engineering, Final Payment, Public Works, Release of Retainage
Attachments: 1. Staff Report

Title

58th Avenue Resurfacing/Reclamation from 26th Street to 49th Street, Release of Retainage and Change Order No. 1 (IRC-1324, FM No. 434840-1-54-01)

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Application for Payment No. 6 to Timothy Rose Contracting, Inc. in the amount of $123,697.73 for release of retainage.