Title
Sector 5 Beach and Dune Restoration Project (IRC1923) APTIM, Work Order No. 2018029-10, Year 2 Post-Construction Environmental Monitoring
Recommended Action
Staff recommends the BCC authorize Work Order No. 2018029-10 in the total lump sum amount of $99,010.41. Additionally, staff recommends the BCC authorize the Chairman to execute Work Order No. 2018029-10