File #: 22-0349    Version: 1
Type: Consent Staff Report Status: Passed
File created: 4/26/2022 In control: Board of County Commissioners
On agenda: 5/3/2022 Final action:
Title: Force Main Replacement Under 49th Street along 58th Avenue
Indexes: 49th Street/58th Avenue, Bid Waiver, Force Main Relocation, Timothy Rose Contracting
Attachments: 1. Staff Report, 2. Timothy Rose Contracting Inc Cost Estimate

Title

Force Main Replacement Under 49th Street along 58th Avenue

Recommended Action

Staff recommends that the Board of County Commissioners waive the requirement for bids and authorize the issuance of a purchase order for the work to Timothy Rose Contracting, Inc., to perform the utility replacement for the amount of $172,293.87.