File #: 21-0749    Version: 1
Type: Consent Staff Report Status: Passed
File created: 8/6/2021 In control: Board of County Commissioners
On agenda: 8/17/2021 Final action:
Title: Final Payment, Release of Retainage and Change Order No. 1 Indian River Boulevard and 8th Street Signalization IRC-1909
Indexes: Change Order, Engineering, Final Payment, Public Works, Release of Retainage
Attachments: 1. Staff Report, 2. Change Order No. 1

Title

Final Payment, Release of Retainage and Change Order No. 1 Indian River Boulevard and 8th Street Signalization IRC-1909

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Contractor’s Application for Payment No. 8 in the amount of $41,856.91 for final payment and release of retainage.