Title: North County Water and Sewer Project Phase 2 Bid No. 2021019, Change Order #1 - Increased Materials Cost
Indexes: Centerline, Inc., Change Order, North County Water and Sewer Project, Phase II
Attachments: 1. Staff Report, 2. Change Order #1 Centerline Inc

Title

North County Water and Sewer Project Phase 2 Bid No. 2021019, Change Order #1 - Increased Materials Cost

Recommended Action

Staff recommends the Board of County Commissioners approve Change Order #1 in the amount of $159,297.70 for the North County Water and Sewer Project Phase 2 and bring the total contract amount to $4,040,566.70