Title
Change Order No. 5 to Thalle (Bid #2018025)
Recommended Action
Solid Waste Disposal District staff recommends that its Board approve and authorize the Chairman to execute Change Order No. 5 approving extension in contract time for Milestone 1, Milestone 2, and Final Completion by 68 days and allow the use of $530,761.05 from contingency funding to Thalle Construction Company, Inc., for the Segment 3 Cell 2 Expansion, Segment 2 Partial Closure and Landfill Gas System Expansion project.