File #: 19-0709    Version: 1
Type: Consent Staff Report Status: Passed
File created: 7/31/2019 In control: Board of County Commissioners
On agenda: 8/13/2019 Final action: 8/13/2019
Title: Work Order No. 8, REI Engineers, Inc. - IRC Courthouse Parking Garage and Seal Replacement (IRC-1801)
Indexes: Engineering, Public Works, Work Order
Attachments: 1. Staff Report, 2. REI Engineers, Inc. Work Order No. 8

Title

Work Order No. 8, REI Engineers, Inc. - IRC Courthouse Parking Garage and Seal Replacement (IRC-1801)

Recommended Action

Staff recommends that the BCC approve Work Order No. 8 for REI Engineers, Inc. to design, assist in bidding, and perform construction administration services for the IRC Courthouse Parking Garage and Seal Replacement project, and authorize the Chairman to execute Work Order No. 8 in the lump sum amount of $50,470.00.