Title
Barrier Island Reclaimed Water Main System Analysis - Results
Recommended Action
Staff recommends that the Indian River County Board of County Commissioners consider the results of the A1A Barrier Island Reuse Water Main Feasibility Study. The report indicates that the east side of the A1A corridor is in fact feasible and cost-competitive with the subaqueous route. It is important to note that John’s Island Water Management is constructing the subaqueous line, and while the County does not have the ability to unilaterally determine the routing of the proposed line, it does and will require the design and construction to meet or exceed industry standards as well as the County’s utility construction requirements