File #: 18-1871    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 5/22/2018 In control: Board of County Commissioners
On agenda: 6/5/2018 Final action:
Title: Pelican Pointe Water Service Replacement: Approval of Change Order and Final Pay for Blue Goose Construction Work Authorization No. 2017-006
Indexes: Blue Goose Construction, Change Order, Final Payment, Pelican Pointe, Water Distribution
Attachments: 1. Staff Report, 2. Change Order No. 1, 3. Blue Goose Final Pay Request

Title

Pelican Pointe Water Service Replacement: Approval of Change Order and Final Pay for Blue Goose Construction Work Authorization No. 2017-006

Recommended Action

Staff recommends that the Board of County Commissioners approve Change Order No. 1 to Work Authorization No. 2017-006 for an additional labor amount of $68,330.95, contractor-purchased materials in the amount of $6,990.86, and to authorize final payment to Blue Goose Construction in the amount of $146,131.56.