Title: 128th Court Water Main Extension: Approval of Change Order and Final Payment of Blue Goose Construction Work Authorization No. 2018-001
Indexes: 128th Court Water Main Extension, Blue Goose Construction, Change Order, Final Payment, Water Distribution
Attachments: 1. Staff Report, 2. Change Order # 1, 3. Final Application for Payment

Title

128th Court Water Main Extension: Approval of Change Order and Final Payment of Blue Goose Construction Work Authorization No. 2018-001

Recommended Action

Staff recommends that the Board of County Commissioners approve Change Order #1 to reduce Work Authorization No. 2018-001 and authorize final payment to Blue Goose Construction in the amount of $34,604.70.