File #: 17-1276    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 12/5/2017 In control: Board of County Commissioners
On agenda: 12/19/2017 Final action:
Title: 8th Street Sidewalk Improvements (58th Avenue to 21st Court) Release of Retainage and Change Order No. 1
Indexes: Change Order, Engineering, FDOT, Final Payment, Public Works, Release of Retainage
Attachments: 1. Staff Report, 2. Contractor's Application for Payment No. 7, 3. Change Order No. 1

Title

8th Street Sidewalk Improvements (58th Avenue to 21st Court) Release of Retainage and Change Order No. 1

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Application for Payment No. 7 to Timothy Rose Contracting, Inc. in the amount of $25,893.30 for release of retainage.