Title: Change Order No. 1 and Release of Retainage South County Park General Use Field IRC Project No. 1425, Bid No. 2016048
Indexes: Change Order, Engineering, IG Building, Public Works, Release of Retainage
Attachments: 1. Staff Report, 2. Guettler Brothers Construction, LLC Pay Application No. 3 FINAL, 3. Change Order No. 1, 4. Description of Itemized Changes

Title

Change Order No. 1 and Release of Retainage South County Park General Use Field IRC Project No. 1425, Bid No. 2016048

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Guettler Brothers Construction, LLC Pay Application No. 03 FINAL for release of retainage in the amount of $14,924.10.