TO: Board of County Commissioners
THROUGH: John A. Titkanich, Jr., County Administrator
Nancy A. Bunt, Assistant County Administrator
Addie Javed, P.E., Public Works Director
Adam Heltemes, P.E., Roadway Production Manager
Richard Reichenbach, P.E., Project Engineer
FROM: Jill Williams, Contract Support Specialist
DATE: June 20, 2025
SUBJECT: Final Payment, Release of Retainage and Change Order No. 4 (IRC-1505)
Construction of 66th Avenue Roadway Widening (49th Street to 69th Street)
IRC-1505, FDOT FM 436379-1-54-01 & 436379-1-54-02
__________________________________________________________________
BACKGROUND
On April 26, 2021, the Board of County Commissioners awarded Bid No. 2021018 to Halley Engineering Contractors, Inc. in the amount of $32,728,137.85 for roadway improvements for 66th Avenue from 49th Street to 69th Street which consists of the widening and reconstruction of the existing roadway to a 4-lane divided roadway section with 5 bridges located within the project limits. Also included are five-foot bike lanes, stormwater drainage improvements, pavement markings, traffic signals and landscape and irrigation improvements.
ANALYSIS
Change Order No. 4 is to make final adjustments to the current contract price of $34,329,232.34 for a decrease to the contract by $1,322,311.29 resulting in a final contract price of $33,006,921.05 and to make final contract time adjustments.
Halley Engineering Contractors, Inc. has completed the project and has been paid $31,550,006.87with $1,660,526.68 held in retainage. ...