Skip to main content
File #: 26-0210    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 1/28/2026 In control: Board of County Commissioners
On agenda: 2/10/2026 Final action:
Title: Administration Building A & B Entrance Concrete Replacement & Trench Drain Installation
Indexes: Administration Building
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.
TO: Board of County Commissioners

THROUGH: John A.Titkanich, Jr., County Administrator
Nancy Bunt, Assistant County Administrator
Anthony Warren, Director of Building & Facilities Services
FROM: Chadwick Bacon, Assistant Director of Building & Facilities Services

DATE: January 28, 2026

SUBJECT: Administration Building A & B Entrance Concrete Replacement & Trench Drain Installation
__________________________________________________________________

BACKGROUND AND ANALYSIS
Staff requests that the Board approve funding for the Administration Building A & B Entrance Concrete Replacement and Trench Drain Installation project at the County Administration Complex to address identified infrastructure deficiencies, safety concerns, and drainage performance issues. As part of the County’s ongoing efforts to maintain durable, accessible, and code-compliant public facilities, improvements to the primary building entrances are required to correct deteriorated concrete surfaces, resolve recurring water intrusion, drainage challenges, and tripping/safety hazards.

The project includes removal and replacement of approximately 2,562 square feet of existing exterior concrete with a new 4-inch, full-depth, colored, textured, and wet-stamped decorative concrete slab reinforced with wire mesh in accordance with FDOT Standard Specification Section 522. Additionally, the project includes installation of 35 linear feet of ADA-compliant Zurn P12-PSR stainless steel reverse punch perforated trench drain, reinforced with continuous #4 rebar, to improve surface water capture and direct integration with the existing drainage system in front of the B Building, this extensive trench system will n...