File #: 22-0125    Version: 1
Type: Consent Staff Report Status: Passed
File created: 2/7/2022 In control: Board of County Commissioners
On agenda: 2/15/2022 Final action:
Title: Release of Retainage and Change Order No. 1, 58th Avenue (From North of 57th Street to 85th Street/CR510), FM No. 436416-1-54-01, IRC-1325
Indexes: Change Order, Engineering, Public Works
Attachments: 1. Staff Report, 2. Change Order No. 1

Title

Release of Retainage and Change Order No. 1, 58th Avenue (From North of 57th Street to 85th Street/CR510), FM No. 436416-1-54-01, IRC-1325

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Contractor’s Application for Payment No. 1325-9 in the amount of $316,570.41 for release of retainage. Once final release of liens from all Timothy Rose Contracting, Inc. suppliers and subcontractors have been received, reviewed and approved, final payment will be processed.