Title: Gifford Neighborhood 45th Street Beautification Project Phase II, Final Payment, Release of Retainage and Change Order No. 1 (IRC-1748)
Indexes: Change Order, Engineering, Public Works
Attachments: 1. Staff Report, 2. Change Order No. 1, 3. Change Order No. 1

Title

Gifford Neighborhood 45th Street Beautification Project Phase II, Final Payment, Release of Retainage and Change Order No. 1 (IRC-1748)

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Application for Payment No. 9 to Johnson-Davis, Inc. in the amount of $126,957.41 for final payment and release of retainage.