Title
Change Order No. 1 to Summit Construction of Vero Beach, LLC
Recommended Action
Solid Waste Disposal District (SWDD) staff recommends that its Board approve the following: a) Approve Change Order No. 1 with Summit Construction of Vero Beach, LLC, for $7,015 to install additional footings, dirt work, as well as installation of a vapor/moisture barrier, and additional time of 90 days on the contract to complete the project; and, b) Authorize the Chairman to execute the same, as presented