File #: 19-0603    Version: 1
Type: Consent Staff Report Status: Passed
File created: 7/2/2019 In control: Board of County Commissioners
On agenda: 7/9/2019 Final action:
Title: Amendment 1 to Work Order No. 1 with Arcadis for Design, Procurement and Construction Administration to Rehabilitate the RAS/WAS Pumps at the Central Wastewater Treatment Plant
Indexes: Amendment, Arcadis, Central WWTF, RAS/WAS Pumps, Rehabilitation, Work Order
Attachments: 1. Staff Report, 2. Work Order No 1 RAS and WAS Pump Replacement
Related files: 21-0367

Title

Amendment 1 to Work Order No. 1 with Arcadis for Design, Procurement and Construction Administration to Rehabilitate the RAS/WAS Pumps at the Central Wastewater Treatment Plant

Recommended Action

Staff recommends that the Board of County Commissioners approve Amendment No.1 to Work Order No. 1 with Arcadis, in the amount of $44,075.00, for Professional Services that include design, specifications/bid documents, and construction observation services to rehabilitate the Return-Activated Sludge/Waste-Activated Sludge pump system and the rotary drum thickener at the Central Wastewater Treatment Facility, and authorize the Chairman to execute said work order on their behalf