File #: 21-0734    Version: 1
Type: Consent Staff Report Status: Passed
File created: 8/4/2021 In control: Board of County Commissioners
On agenda: 8/17/2021 Final action:
Title: Work Order No. 7 with Kimley-Horn and Associates - South County Reverse Osmosis Water Treatment Plant 2022 Permit Renewal
Indexes: Kimley-Horn and Associates, Permit Renewal, South RO Water Treatment Facility
Attachments: 1. Staff Report, 2. Work Order No 7 - Scope of Services

Title

Work Order No. 7 with Kimley-Horn and Associates - South County Reverse Osmosis Water Treatment Plant 2022 Permit Renewal

Recommended Action

Staff recommends that the Board of County Commissioners approve Work Order No. 7 with Kimley-Horn and Associates, for $32,200.00, with $15,000.00 coming from Fiscal Year 2020-2021 and $17,200.00 coming from Fiscal Year 2021-2022, and authorize the Chairman to execute the same, as presented