Title
Work Order No. 7 with Kimley-Horn and Associates - South County Reverse Osmosis Water Treatment Plant 2022 Permit Renewal
Recommended Action
Staff recommends that the Board of County Commissioners approve Work Order No. 7 with Kimley-Horn and Associates, for $32,200.00, with $15,000.00 coming from Fiscal Year 2020-2021 and $17,200.00 coming from Fiscal Year 2021-2022, and authorize the Chairman to execute the same, as presented