Skip to main content
File #: 26-0235    Version: 1
Type: Consent Staff Report Status: Passed
File created: 2/9/2026 In control: Board of County Commissioners
On agenda: 2/24/2026 Final action:
Title: Hampton Park PD Phase 2 Request from Developer, Meritage Homes of Florida, Inc., for an Extension to Complete Required Improvements
Attachments: 1. Letter Requesting Extension - Hampton Park PD Phase 2, 2. Modification extension - Hampton Park PD Phase 2
TO: Board of County Commissioners

THROUGH: John A. Titkanich, Jr., County Administrator

FROM: Susan J. Prado, Deputy County Attorney

DATE: February 9, 2026

SUBJECT: Hampton Park PD Phase 2
Request from Developer, Meritage Homes of Florida, Inc., for an Extension to Complete Required Improvements
__________________________________________________________________

BACKGROUND
The final plat for Hampton Park PD Phase 2 was approved by the Board of County Commissioners on March 11, 2025 and the developer, Meritage Homes of Florida, Inc., a Florida profit corporation posted a Regions Bank Irrevocable Letter of Credit No. 55111484 in the amount of $216,617.91 (expiring on May 26, 2026) to guaranty the construction of the required improvements and entered into a Contract for Construction of Required Improvements No. PD-21-04-04 (2004040192-96959).

Developer has not yet completed the required improvements and by letter dated February 10, 2026, has requested an extension to February 25, 2027 to complete the required improvements. The developer will present an amendment to the existing letter of credit which extends the letter of credit expiration date to May 25, 2027 and is 90 days beyond the requested extension date.

Section 913.10(1)(E) of the County Code states that for good cause shown the Board may in its discretion grant one or more extensions of time for performance of any contract for construction of required improvements provided the surety supporting such contract remains valid for the required 90-day period following the newly extended time for performance.

Engineering has no objection to the requested extension to complete the required improvements, as the homes in this phase have not yet begun to be constructed.

BUDGETARY IMPACT
There is no cost to the County associated with extending the completion deadline to February 25, 2027.

POTENTIAL FUTURE BOARD ACTIONS
Future extension of contract, or pulling of security.

STAFF RECOMME...