File #: 19-0850    Version: 1
Type: Consent Staff Report Status: Passed
File created: 9/6/2019 In control: Board of County Commissioners
On agenda: 9/17/2019 Final action: 9/17/2019
Title: Wabasso Causeway Fishing Pier Demolition Project (IRC-1712), Release of Retainage and Change Order No. 1
Indexes: Engineering, Public Works, Release of Retainage
Attachments: 1. Staff Report, 2. Change Order No. 1, 3. Description of Itemized Changes
Related files: 24-0194

Title

Wabasso Causeway Fishing Pier Demolition Project (IRC-1712), Release of Retainage and Change Order No. 1

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Contractor’s Application for Payment No. 3 to Underwater Engineering Services, Inc. in the amount of $35,890.40 for release of retainage.