File #: 20-1676    Version: 1
Type: Consent Staff Report Status: Passed
File created: 6/23/2020 In control: Board of County Commissioners
On agenda: 7/7/2020 Final action: 7/7/2020
Title: 49th Street Milling & Resurfacing, Release of Retainage and Change Order No. 1 (IRC-1414) 
Indexes: Change Order, Engineering, FDOT, Public Works, Release of Retainage
Attachments: 1. Staff Report, 2. Change Order No. 1

Title

49th Street Milling & Resurfacing, Release of Retainage and Change Order No. 1 (IRC-1414) 

Recommended Action

Staff recommends approval of Change Order No. 1 and payment of Contractor’s Application for Payment No. 7 to Guettler Brothers Construction, LLC in the amount of $43,404.78 for release of retainage. Once final release of liens from all Guettler Brothers Construction, LLC suppliers and subcontractors have been received, reviewed and approved, final payment will be processed.