Title
Change Order No. 3 66th Avenue Roadway Widening (49th Street to 69th Street), Construction of 53rd Street Signalized Intersection, IRC-1505
Recommended Action
Staff recommends the Board approve Change Order No. 3, authorizing the additional funding in the amount of $814,277.14. The new total contract amount will be $34,329,232.34.