Skip to main content
File #: 25-0970    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 9/24/2025 In control: Solid Waste Disposal District
On agenda: 10/7/2025 Final action: 10/7/2025
Title: Change Order No. 2 to CK Contractors and Development (CK) for Automated Scale Lane Project
Indexes: Automated Scale Lane, CK
Attachments: 1. Automated Scale CO 2
TO: The Solid Waste Disposal District Board of Commissioners

THROUGH: John A. Titkanich, Jr., County Administrator
Sean C. Lieske, Director of Utility Services

FROM: Himanshu H. Mehta, PE, Managing Director, Solid Waste Disposal District

DATE: September 24, 2025

SUBJECT: Request for Approval of Change Order No. 2 to CK Contractors and Development (CK) for Landfill Automated Scale Lane Project
__________________________________________________________________

BACKGROUND
The Solid Waste Disposal District (SWDD) staff utilized the Department of Utility Services' labor contract (originally approved on July 7, 2020, and ending on July 6, 2024) to authorize the construction of the Automated Scale Lane Project that was designed and permitted by Kimley-Horn and Associate, Inc. (KHA) under separate authorizations from the SWDD Board.

Specifically, CK Contractors and Development (CK) was issued a Purchase Order (PO) #98761 for the Automated Scale Lane project in the amount of $475,176.89. On March 11, 2025, the SWDD Board approved Change Order No. 1 in the amount of $229,026.47 to CK for a total project cost of $704,203.36.

To enhance customer service, and provide proper ingress and egress, lift arms, and roadways, as well as additional cameras, staff requested additional scope to the project.

CK has requested Change Order No. 2 to complete the project, which requires SWDD Board approval.

ANALYSIS
The current in-bound and out-bound lift arms are out of service, and the existing roadways leading to these scales need to be improved. Additional cameras are also needed to manage the new automated scale. These improvements are best facilitated as part of the automated scale lane project. Given that CK and their subcontractor, Summit Construction, is already mobilized to the site, staff requested these additional services to the existing project. CK has submitted the attached Change Order No. 2 in the amount of $293,429.40.

The purpose of this change o...