Title
Change Order No. 4 to Thalle (Bid #2018025)
Recommended Action
The Solid Waste Disposal District recommends that its Board approve and authorize the Chairman to execute Change Order No. 4 approving the extension in contract time for Milestone 1, Milestone 2, and Final Completion by 57 days and allow the use of $855,955.37 from contingency funding to Thalle Construction Company, Inc., for the Segment 3 Cell 2 Expansion, Segment 2 Partial Closure and Landfill Gas System Expansion project