File #: 18-1796    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 4/30/2018 In control: Board of County Commissioners
On agenda: 5/8/2018 Final action:
Title: Work Order No. 2, Kimley-Horn & Associates, Inc. 43rd Avenue & 26th Street Intersection Improvements (IRC-1808)
Indexes: Engineering, Engineering Services, Kimley-Horn and Associates, Public Works, Work Order
Attachments: 1. Staff Report, 2. Work Order No. 2

Title

Work Order No. 2, Kimley-Horn & Associates, Inc. 43rd Avenue & 26th Street Intersection Improvements (IRC-1808)

Recommended Action

Staff recommends approval of Work Order No. 2 to Kimley-Horn & Associates, Inc., authorizing the professional services as outlined in the Scope of Services (Exhibit A) and requests the Board authorize the Chairman to execute Work Order No. 2 on their behalf for a lump sum amount of $120,000.00.