TO: Indian River County Board of County Commissioners

THROUGH: John Titkanich, County Administrator
Sean Lieske, Director of Utilities
Howard Richards, P.E., Capital Projects Manager

FROM: Harrison Youngblood, P.E., Principal Engineer

DATE: February 6, 2026

SUBJECT: Final Pay to Kimley-Horn and Associates for Work Order No.4 under RFQ2019070 for Supervisory Control and Data Acquisition System Upgrades Part A at Oslo Water Production Facility, IRCDUS Project ID 12.19.536
__________________________________________________________________

BACKGROUND
On April 20 2021, the Indian River County Board of County Commissioners (BCC) approved Work Order No.4 (WO4) for professional services with Kimley-Horn and Associates, Inc. (KHA) under RFQ 2019070 for engineering services associated with the Supervisory Control and Data Acquisition System (SCADA) improvements at the Oslo Water Production Facility (WPF). KHA utilized the services and provided coordination of Control Systems Design, Inc. (CSD), and C&W Engineering for SCADA system integration and electrical engineering in the execution of the project tasks.

KHA prepared bid documents consisting of site plans depicting improvements which are needed for present and future phasing, and panel drawings and specifications for replacement and installation of new Remote Input/Output (RIO) and Programable Logic Controller (PLC) panels. The drawings depicted modifications to the Main PLC and the proposed High Service Pump PLC. KHA provided coordination with Indian River County Department of Utility Services (IRCDUS) and the Indian River County (IRC) purchasing department for bidding the proposed improvements. KHA also provided construction phase services and coordination between the Contractor, Owner, Electrical Engineer, and Integrator. KHA also reviewed and completely vetted the current Human Machine Interface (HMI) migration to VTScada, tested and verified operations local and with all external systems. Ch...