Title
CR512 & N. Broadway Street Drainage Restoration (IRC-2006), Change Order No. 1
Recommended Action
Staff recommends the Board approve Change Order No. 1 increasing the contract time by 44 days and additional funding in the amount of $211,108.00 for a new contract total of $426,342.70. Staff further recommends the Board authorize the Chairman to execute said Change Order No. 1 after review and approval by the County Attorney as to form and legal sufficiency.