File #: 24-1006    Version: 1
Type: Consent Staff Report Status: Passed
File created: 12/4/2024 In control: Board of County Commissioners
On agenda: 12/17/2024 Final action:
Title: CR512 & N. Broadway Street Drainage Restoration (IRC-2006), Change Order No. 1
Indexes: Change Order, Engineering, Public Works
Attachments: 1. Staff Report, 2. Change Order No. 1
Related files: 24-0417

Title

CR512 & N. Broadway Street Drainage Restoration (IRC-2006), Change Order No. 1

Recommended Action

Staff recommends the Board approve Change Order No. 1 increasing the contract time by 44 days and additional funding in the amount of $211,108.00 for a new contract total of $426,342.70. Staff further recommends the Board authorize the Chairman to execute said Change Order No. 1 after review and approval by the County Attorney as to form and legal sufficiency.