Skip to main content
File #: 25-0990    Version: 1
Type: Consent Staff Report Status: Passed
File created: 10/6/2025 In control: Board of County Commissioners
On agenda: 10/21/2025 Final action:
Title: Florida Power & Light Easements Sandridge Golf Club – New Clubhouse
Indexes: FPL, Sandridge Golf Course
Attachments: 1. FPL Overhead Easement, 2. FPL Underground Easement
TO: Board of County Commissioners

THROUGH: John A. Titkanich, Jr., County Administrator
Nancy A. Bunt, Assistant County Administrator
Anthony Warren, Director - Building & Facility Services

FROM: Robert S. Skok, Capital Projects Manager

DATE: October 6, 2025

SUBJECT: Florida Power & Light Easements
Sandridge Golf Club - New Clubhouse

__________________________________________________________________

BACKGROUND
Sandridge Golf Club is under construction to build a new Clubhouse and County staff is overseeing administration of the Contract. Florida Power & Light (FPL) has requested the County grant two easements on the County owned property for installation of the power from the public right-of-way to the new building location. The County Surveyor worked with an FPL representative for the location of the easements. The County Surveyor has created signed and sealed sketch and legal description documents to detail the easement area within the property.

BUDGETARY IMPACT
The cost of recording the documents will be approximately $55.40. The cost will be funded from the Sandridge Clubhouse/Event Space account, number 418-169000-21018.

STRATEGIC PLAN ALIGNMENT
Quality of Life

STAFF RECOMMENDATION
Recommended Action
Staff recommends the Board of County Commissioners approve the easements to Florida Power & Light in accordance with the attached sketch and description, authorize the County Attorney’s office to finalize the legal documents to record the approved easement and authorize the Chair to execute the final legal documents to effectuate the granting of t...