Title: Change Order No. 1, 66th Avenue over North Relief Canal Bridge, IRC-1505
Indexes: 66th Avenue, Change Order, Engineering, Public Works
Attachments: 1. Staff Report, 2. Change Order No. 1

Title

Change Order No. 1, 66th Avenue over North Relief Canal Bridge, IRC-1505

Recommended Action

Staff recommends approving Change Order No. 1 authorizing the $55,000.00 reduction to the contract with HEC.  The new total contract price will be $32,673,137.85.