File #: 23-0165    Version: 1
Type: Consent Staff Report Status: Passed
File created: 2/14/2023 In control: Board of County Commissioners
On agenda: 2/21/2023 Final action:
Title: Work Order 14 to Bowman Consulting Group, LTD. - Replacement of the NWWTF 24” Force Main
Indexes: Bowman Consulting Group, Force Main Replacement, North Wastewater Treatment Facility, Work Order
Attachments: 1. Staff Report, 2. Work Order No 14 Bowman Consulting Group

Title

Work Order 14 to Bowman Consulting Group, LTD. - Replacement of the NWWTF 24” Force Main

Recommended Action

Staff recommends that the Board of County Commissioners approve Work Order 14 for Bowman Consulting Group, LTD., to provide professional services for the force main replacement in the amount, not to exceed, of $88,230.00, and authorize the Chairman to sign on their behalf