File #: 25-0688    Version: 1
Type: Consent Staff Report Status: Passed
File created: 6/20/2025 In control: Board of County Commissioners
On agenda: 7/15/2025 Final action:
Title: Final Payment, Release of Retainage and Change Order No. 4 (IRC-1505) Construction of 66th Avenue Roadway Widening (49th Street to 69th Street) RC-1505, FDOT FM 436379-1-54-01 & 436379-1-54-02
Indexes: 66th Avenue, Engineering, Final Payment, Public Works, Release of Retainage
Attachments: 1. Change Order No. 4, 2. HEC Pay App 49

TO:                                                                    Board of County Commissioners

 

THROUGH:                                           John A. Titkanich, Jr., County Administrator

                                                                                    Nancy A. Bunt, Assistant County Administrator

                                                                                    Addie Javed, P.E., Public Works Director

                                                                                    Adam Heltemes, P.E., Roadway Production Manager

                                                                                    Richard Reichenbach, P.E., Project Engineer

 

FROM:                                                              Jill Williams, Contract Support Specialist

 

DATE:                                                               June 20, 2025

 

SUBJECT:                                          Final Payment, Release of Retainage and Change Order No. 4 (IRC-1505)

                                                                                    Construction of 66th Avenue Roadway Widening (49th Street to 69th Street)

IRC-1505, FDOT FM 436379-1-54-01 & 436379-1-54-02

__________________________________________________________________

 

BACKGROUND

On April 26, 2021, the Board of County Commissioners awarded Bid No. 2021018 to Halley Engineering Contractors, Inc. in the amount of $32,728,137.85 for roadway improvements for 66th Avenue from 49th Street to 69th Street which consists of the widening and reconstruction of the existing roadway to a 4-lane divided roadway section with 5 bridges located within the project limits. Also included are five-foot bike lanes, stormwater drainage improvements, pavement markings, traffic signals and landscape and irrigation improvements.

ANALYSIS

Change Order No. 4 is to make final adjustments to the current contract price of $34,329,232.34 for a decrease to the contract by $1,322,311.29 resulting in a final contract price of $33,006,921.05 and to make final contract time adjustments.

Halley Engineering Contractors, Inc. has completed the project and has been paid $31,550,006.87with $1,660,526.68 held in retainage. Halley Engineering Contractors, Inc. has submitted Contractor’s Application for Payment 1505-49 FINAL in the amount $1,456,914.18 ($1,660,526.68 for retainage and ($203,612.50) for a final payment due of $1,456,914.18).

BUDGETARY IMPACT

Funding in the amount of $1,456,914.18 is budgeted and available from the following accounts:

Account Name: Optional Sales Tax/66th Ave/49th St - 69th St

Account Number: 31521441-066510-07806

Amount: ($203,612.50)

Account Name: Traffic Impact Fees/District 2/66th Ave (49th St - 69th St)/Retainage-Halley Eng Contractors

Account Number: 102-206002-07806

Account Amount: $302,776.22

Account Name: Traffic Impact Fees/District 1/66th Ave (49th St - 69th St)/Retainage - Halley Eng Contractors

Account Number: 104-206000-07806

Amount: $228,326.36

Account Name: Optional Sales Tax/66th Ave (49th St - 69th St)/Retainage - Halley Eng Contractors

Account Number: 315-206001-07806

Amount: $1,129,424.10

 

PREVIOUS BOARD ACTIONS

Three change orders have been approved by the Board of County Commissioners to date. Change Order No. 1 incorporated redesign of the 66th Avenue Bridge over the North Relief Canal for a reduction to the contract total in the amount of $55,000.00 and was approved on September 21, 2021. Change Order No. 2 was approved on April 12, 2022 and provided construction of a modified bridge design to widen 53rd Street Bridge over Lateral A Canal from 3-lanes to 5-lanes in the amount of $841,817.35. Change Order No. 3 provided construction of a signalized intersection at 66th Avenue and 53rd Street to improve safety in the amount of $814,277.14 and was approved by the Board on January 31, 2023. The contract total after approval of all three change orders is $34,329,232.34.

STAFF RECOMMENDATION

Recommended Action

Staff recommends approval of Change Order No. 4 and payment of Contractor’s Application for Payment No. 1505-49 FINAL in the amount of $1,456,914.18, once all subcontractor final lien releases have been received.