Title: Amendment No. 1 to Work Order No. 2 to Jones Edmunds for 74th Avenue SW Widening Project
Indexes: 74TH AVE SW, Jones Edmunds & Associates
Attachments: 1. Staff Report & Jones Edmunds WO2 - 2025-05-07, 2. Amend No 1 to WO No 2.pdf

TO:                                                    The Solid Waste Disposal District Board of Commissioners

 

THROUGH:                                          John A. Titkanich, Jr., County Administrator

                                                               Sean C. Lieske, Director of Utility Services

 

FROM:                                          Himanshu H. Mehta, PE, Managing Director, Solid Waste Disposal District

 

DATE:                                          May 7, 2025

 

SUBJECT:                                          Amendment No. 1 to Work Order No. 2 to Jones Edmunds for 74th Avenue SW Widening Project

__________________________________________________________________

 

BACKGROUND

On September 10, 2024, the Solid Waste Disposal District (SWDD) approved Work Order No. 2 for $174,920 to Jones Edmunds and Associates, Inc. (Jones Edmunds) to provide engineering design, permitting, and bidding services for widening of the landfill entrance as well as a dedicated right turn lane on 74th Avenue SW to optimize the efficiency of the upcoming automated scale system.

 

The purpose of this agenda is to request a change order to cover cost for additional off-site survey/data collection.

 

ANALYSIS

The scope of work included survey/data collection in the amount of $18,000. However, staff have requested survey/data collection for an additional 800 feet, which has conversely required additional effort and cost from Jones Edmunds. Jones Edmunds has proposed to utilize Masteller, Moler & Taylor for the additional survey work and is requesting a change order in the amount of $6,455 to cover the additional work. Staff supports the need for additional work and the accompanying change order which would increase the total project cost to $181,375.

 

BUDGETARY IMPACT

Funding, in the amount of $6,455, for Amendment No. 1 to Work Order No. 2 for the 74th Avenue SW Widening Project is budgeted and available in the SWDD/WIP/74th Ave Turn Lane, Gate & Cameras account, number 411-169000-23042, which is funded from SWDD assessments and user fees.

Description

Account

Amount

SWDD/WIP/74th Ave Turn Lane, Gate & Cameras

411-169000-23042

$6,455

 

PREVIOUS BOARD ACTIONS

On September 10, 2024, the SWDD Board approved Work Order No. 2  with Jones Edmunds and Associates, Inc. for $174,920, to provide engineering services related to the 74th Avenue SW Widening project.

 

POTENTIAL FUTURE BOARD ACTIONS

n/a

 

STRATEGIC PLAN ALIGNMENT

Infrastructure

 

OTHER PLAN ALIGNMENT

n/a

 

STAFF RECOMMENDATION

Recommended Action

Solid Waste Disposal District staff recommends that its Board approve Amendment No. 1 to Work Order No. 2 with Jones Edmunds and Associates, Inc. for $6,455, to provide engineering services related to the 74th Avenue SW Widening project; and authorize the Chairman to execute the same, as presented.