File #: 25-0745    Version: 1
Type: Consent Staff Report Status: Agenda Ready
File created: 7/3/2025 In control: Board of County Commissioners
On agenda: 7/15/2025 Final action:
Title: Work Order Number 2, Amendment No. 4 - New Restroom Facility at Fran Adams Park
Indexes: Amendment, Fran Adams, Restrooms, Work Order
Attachments: 1. CCNA 2023 Work Order Template.pdf, 2. 20016_WO2_AmendNo4_25-0703.pdf
Related files: 24-0367, 23-0836, 20-1853, 23-0071
Date Ver.Action ByActionResultAction DetailsMeeting DetailsVideo
No records to display.

TO:                                                    The Honorable Board of County Commissioners

 

THROUGH:                                          John A. Titkanich, Jr., County Administrator

                                          Michael C. Zito, Deputy County Administrator

                                          Beth Powell, Parks, Recreation, & Conservation Director

 

FROM:                                          Wendy Swindell, Parks, Recreation & Conservation Assistant Director

 

DATE:                                          July 3, 2025

 

SUBJECT:                                          Work Order Number 2, Amendment No. 4 - New Restroom Facility at Fran Adams Park

__________________________________________________________________

 

BACKGROUND

On April 17, 2018, the Board of County Commissioners approved Continuing Consulting Engineering Service Agreements for RFQ 2018008 between Indian River County and Masteller and Moler, Inc. and on May 18, 2021, Renewal and Amendment No.1 was executed for continuing engineering services.

 

On August 18, 2020, the Board Approved Work Order Number 2 for Masteller and Moler, Inc., in the amount of $47,610 for design and engineering services for a new restroom facility at Fran Adams Park. On January 31, 2023, the Board approved Amendment No. 1 to Work Order 2 in the amount of $12,065 for revised engineering design services and preparation of construction plans, revised electrical engineering services, permit re-acquisition and preparation of permit application responses. On September 26, 2023, the Board approved Amendment No. 2 to Work Order Number 2 in the amount of $2,810 for Revised Electrical Engineering services and additional permit application responses. On April 23, 2024, the Board approved Amendment No. 3 to Work Order Number 2 for construction administration services in the amount of $3,130; the fee in the original Work Order of $4,510.00 was based on a prefabricated building and no parking upgrades. When the project scope was modified to include architectural design and an ADA access pathway, there was a need for additional construction administration services to complete the project. 

 

ANALYSIS

In 2021, the previous Parks and Recreation Director authorized payment of reimbursable expenses, including project permit fees, by the contractor. These fees totaled $2,845. Amendment No. 4 will increase the project budget by $3,500 and will address the 2021 reimbursable fees, as well as allow for minor reimbursable costs that may arise prior to the completion of the project this year.

 

BUDGETARY IMPACT

Funding, in the amount of $3,500, will come from the Impact Fees/Parks/Improvements/North Co. Soccer Field Improvements account, number 10321072-066390-16005.

 

PREVIOUS BOARD ACTIONS

1.                     20-1853 - August 18, 2020, the Board Approved Work Order Number 2 for Masteller and Moler, Inc., in the amount of $47,610 for design and engineering services for a new restroom facility at Fran Adams Park.

2.                     23-0023 - January 31, 2023, the Board approved Amendment No. 1 to Work Order 2 in the amount of $12,065 for revised engineering design services and preparation of construction plans, revised electrical engineering services, permit re-acquisition and preparation of permit application responses.

3.                     23-0836 - September 26, 2023, the Board approved Amendment No. 2 to Work Order Number 2 in the amount of $2,810 for Revised Electrical Engineering services and additional permit application responses.

4.                     24-0367 - April 23, 2024, the Board approved Amendment No. 3 to Work Order Number 2 for construction administration services in the amount of $3,130.

 

POTENTIAL FUTURE BOARD ACTIONS

None

 

STRATEGIC PLAN ALIGNMENT

Quality of Life

 

OTHER PLAN ALIGNMENT

N/A

 

STAFF RECOMMENDATION

Recommended Action

Staff respectfully request the approval of Work Order Number 2, Amendment No.4, in the amount of $3,500, for reimbursable expenses associated with the new restroom at Fran Adams Regional Park.