Title: Final Pay to Geosyntec for Work Order No. 1, Amendment 1, 2 & 3 - Segment 3 Cell 3 Liner Construction, Indian River County Landfill Facility
Indexes: Final Payment, Geosyntec, Solid Waste Disposal District
Attachments: 1. Geosyntec Completion Report, 2. Geosyntec Final Invoice

TO:                                                    The Solid Waste Disposal District Board of Commissioners

 

THROUGH:                                          John A. Titkanich, Jr., County Administrator

 

THROUGH:                                          Sean C. Lieske, Director of Utility Services

 

FROM:                                          Himanshu H. Mehta, PE, Managing Director, Solid Waste Disposal District

 

DATE:                                          June 4, 2025

 

SUBJECT:                                                               Final Pay to Geosyntec for Work Order No. 1, Amendment 1, 2 & 3 - Segment 3 Cell 3 Liner Construction, Indian River County Landfill Facility

 

__________________________________________________________________

 

BACKGROUND

On February 20, 2024, the Solid Waste Disposal District (SWDD) Board approved CCNA-2023 - Work Order No. 1, Amendment No. 1, to Geosyntec Consultants, Inc. in the amount of $667,145.14; followed by the approval of Amendment No. 2 on August 20, 2024, in the amount of $170,505.20; and the approval of Amendment No. 3 on December 3, 2024, in the amount of $99,882.08, for a total authorization of $937,532.42 for the Segment 3 Cell 3 Liner Construction Project.

 

Geosyntec’s authorized scope of work included general consulting/meeting support/ project management, preparation of construction documents, quality assurance/quality control services, construction management, resident engineering and certification services, installation of groundwater monitoring wells, financial assurance cost estimate, and miscellaneous engineering support services.

 

ANALYSIS

Geosyntec has satisfactorily completed all of the tasks described in the scope of work for a total invoiced amount of $937,513.16, which includes the final invoice of $12,418.18. Hence, the total project did not exceed budget.  Attached is Geosyntec’s letter report describing in more details the services provided under this work order.

 

BUDGETARY IMPACT

Funding for site preparation of Segment 3, Cell 3 is budgeted and available in the SWDD/WIP/Cell 3 Landfill Expansion account number 411-169000-22034, for a total amount of $12,418.18.

 

Description

Account Number

Amount

SWDD/WIP/Cell 3 Landfill Expansion

411-169000-22034

$12,418.18

 

PREVIOUS BOARD ACTIONS

Item 15.B.2, File #24-0161, was approved by the SWDD Board on February 20, 2024.

Item 15.B.3, File #24-0675, was approved by the SWDD Board on August 20, 2024.

Item 16.B.3, File #24-0964, was approved by the SWDD Board on December 3, 2024.

 

STRATEGIC PLAN ALIGNMENT

Infrastructure

 

STAFF RECOMMENDATION

Recommended Action

Solid Waste Disposal District staff recommends that its Board approve Geosyntec’s final invoice amount of $12,418.18.